EcoGraf Limited · ISIN: AU000000KNL2 · Newswire (Unternehmen)
Land: Australien · Primärmarkt: Australien · EQS NID: 2012963
22 Oktober 2024 08:30AM

Epanko Front-End Engineering Design Completed


EQS-News: EcoGraf Limited / Key word(s): Miscellaneous
Epanko Front-End Engineering Design Completed

22.10.2024 / 08:30 CET/CEST
The issuer is solely responsible for the content of this announcement.


 

Epanko Front-End Engineering Design Completed

Pre-Development Tailings Storage Facility and Water Storage Facility Drilling Works Completed

EcoGraf Limited (ASX: EGR; FSE: FMK; OTCQB: ECGFF) is pleased to advise the Epanko Graphite Project (Epanko or the Project) Front-End Engineering Design (FEED) is now completed.

Completion of the FEED study by METC Engineering and Construction (METC) in conjunction with their Tanzanian joint-venture operation, METC-PaulSam, provides for the overall control base for the execution of the Project. The FEED study output included designs for all disciplines and developed the scope of work, schedule and control budget for the process plant. 

The updated process plant design for the Project is based on proven metallurgical processes that optimises recovery and minimises operating costs.  Equipment selection has been based upon test work results, vendor advice, BFS recommendations and METC data base and experience. The layout of the Plant has been optimised to improve operability, ease of maintenance access and to minimise capital costs.

The outcomes of the FEED study are currently being reviewed as part of the current due diligence for the debt financing.  

This follows the completion of the final layout design for the Stage 1 - 73,000tpa graphite process plant (See ASX announcement dated 25 July 2024).

Dear customer, if you don't see the video, click here

View flyover video: https://youtu.be/a-k6VhApfWY

 

Engineering geotechnical drilling program completed

The Company is also pleased to advise that the engineering geotechnical drilling program commenced in August is now completed.  The program provides critical samples and data that will allow EcoGraf to finalise the geotechnical parameters for the proposed Epanko Processing Plant, Tailings Storage Facility (TSF) and Water Storage Facility (WSF) and will ensure that the final TSF design meets the engineering standards outlined in the new 2020 Global Industry Standard on Tailings Management (GISTM). 

The program was supervised by leading engineering consulting group Knight Piésold and included the completion of 19 holes for geotechnical drilling and 68 geotechnical test pits.  The 2024 work supplements the 2023 TSF geotechnical drilling and test pits, concluding all pre-construction geotechnical field programs.

fncls.ssp?fn=download2_file&code_str=4dbb802011582202b1d4b6655210abe9

This announcement is authorised for release by Andrew Spinks, Managing Director.

 

 

For further information, please contact:

INVESTORS 

Andrew Spinks  

Managing Director 

T: +61 8 6424 9002

 

Competent Person Statement

The information in this report that relates to Mineral Resources is based on, and fairly reflects, information compiled by Mr. David Williams and Mr. David Drabble. Mr. David Williams is a full-time employee of ERM and is a Member of the Australian Institute of Geoscientists (#4176)(RPGeo). Mr. David Drabble is a full-time employee of EcoGraf Ltd and is a Member of the Australasian Institute of Mining and Metallurgy (#307348). Mr David Williams and Mr David Drabble have sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity which they are undertaking to qualify as Competent Persons as defined in the 2012 Edition of the Australasian Code for the Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code). The Company confirms that it is not aware of any new information or data that materially affects the information included in the relevant market announcement and all material assumptions and technical parameters underpinning the estimates continue to apply and have not materially changed.

 

 

About EcoGraf

EcoGraf is building a vertically integrated battery anode materials business to produce high purity graphite products for the lithium-ion battery and advanced manufacturing markets. Over US$30 million has been invested to date to create a highly attractive graphite mining and mineral processing business.

In Tanzania, the Company is developing the TanzGraphite natural flake graphite business, commencing with the Epanko Graphite Project, to provide a long-term, scalable supply of feedstock for EcoGraf™ battery anode material processing facilities, together with high quality large flake graphite products for specialised industrial applications.

Using its environmentally superior EcoGraf HFfree™ purification technology, the Company will upgrade the flake graphite to produce 99.95%C high performance battery anode material to supply electric vehicle, battery and anode manufacturers in Asia, Europe and North America as the world transitions to clean, renewable energy. 

Battery recycling is critical to improving supply chain sustainability and the Company’s successful application of the EcoGraf™ purification process to recycle battery anode material provides it with a unique ability to support customers to reduce CO2 emissions and lower battery costs.

Follow EcoGraf on LinkedIn, Twitter, Facebook and YouTube or sign up to the Company’s mailing list for the latest announcements, media releases and market news.

 

 

 

 



22.10.2024 CET/CEST Dissemination of a Corporate News, transmitted by EQS News - a service of EQS Group AG.
The issuer is solely responsible for the content of this announcement.

The EQS Distribution Services include Regulatory Announcements, Financial/Corporate News and Press Releases.
Archive at www.eqs-news.com


2012963  22.10.2024 CET/CEST

fncls.ssp?fn=show_t_gif&application_id=2012963&application_name=news&site_id=boersengefluester~~~ace3d64b-2049-452a-8d18-fbc8044c4b5f






Member of 3R/RSQ Network
Digital Content
Network Alliance
Transparency · Reliability · Credibility
Information regarding Product Information
Freitag, 22.11.2024, Kalenderwoche (KW) 47, 327. Tag des Jahres, 39 Tage verbleibend bis EoY.